Slide 1: Cutover Planning and Management
Slide 1 / 16

Cutover Planning and Management

TM Chapter 21
[name smudged] · Jason Martin
Seth Anderson · Kristina Dahl

Slide 2: What is Cutover?
Slide 2 / 16

What is Cutover?

  • Transition from an old system to a new one
    • Disrupts organization
    • Object is to minimize disruption through planning
    • New system should make employees more productive with proper training on new plaem.
Slide 3: Planning the Cutover
Slide 3 / 16

Planning the Cutover

  • Divide and conquer tasks with teams
  • Decide whether to re-use some existing facilities
  • Train users how to operate new equipment
Slide 4: Station and Trunk Reviews
Slide 4 / 16

Station and Trunk Reviews

  • Develop information for programming switch or network
    • establish standards
    • determine storage space
  • Floor plans should show telecom outlet locations
    • station types
    • port assignments
    • other identifying info
Slide 5: Cutover Task Lists
Slide 5 / 16

Cutover Task Lists

  • System Procurement
    • Determine system requirements
    • Develop requests for proposals
    • Select the system
    • Negotiate contract
Slide 6: Cutover Task Lists
Slide 6 / 16

Cutover Task Lists

  • Cutover Planning
    • Determine trunk transition methods & quantities
    • Plan station requirements
    • Develop training plan & cutover schedule
    • Develop testing methods & security measures
    • Develop station numbering plan
Slide 7: Cutover Task Lists
Slide 7 / 16

Cutover Task Lists

  • Station Work
    • Conduct station reviews
    • Develop class of service plan
    • Develop wiring plan
    • Develop voice mail plans
    • Assign station numbers
    • Place station wiring and equipment
    • Install software
Slide 8: Cutover Task Lists
Slide 8 / 16

Cutover Task Lists

  • Equipment Room
    • Select Location
    • Prepare equipment room
    • Prepare electrical wiring
    • Prepare HVAC
Slide 9: Cutover Task Lists
Slide 9 / 16

Cutover Task Lists

  • Equipment Installation
    • Place equipment and trunk orders
    • Install equipment
    • Test equipment
    • Conduct acceptance testing
Slide 10: Cutover Task Lists
Slide 10 / 16

Cutover Task Lists

  • Initialize Software
    • Prepare station & trunk translations
    • Program least-cost routing
    • Prepare toll fraud barriers
    • Set up voice mail boxes
    • Initialize call accounting software
Slide 11: Cutover Task Lists
Slide 11 / 16

Cutover Task Lists

  • Operational Functions
    • Develop contingency & intercept plans
    • Reprint telephone directory & stationary
    • Set up help desk
    • Develop trouble reporting procedures
    • Train users
Slide 12: Cutover Task Lists
Slide 12 / 16

Cutover Task Lists

  • Postcutover Activities
    • Follow up on training effectiveness
    • Check on least cost routing
    • Follow up on trunk quantities
    • Check billing
    • Accept system (or reject it!)
Slide 13: PBX Station Reviews
Slide 13 / 16

PBX Station Reviews

  • Most PBXs offer 5 types of terminals:
    • Single-line analog set
    • Single-line digital set with feature buttons
    • Multiple-line set with feature buttons
    • Multiple-line set with digital display
    • ISDN set
Slide 14: Fall Back Plan
Slide 14 / 16

Fall Back Plan

  • A fall back plan is necessary
    • What is probability of delay?
    • What other projects depend on plan completion?
    • What factors could cause delay?
    • What alternatives are available to hold the schedule despite delays?
Slide 15: Testing The New System
Slide 15 / 16

Testing The New System

  • Physical inspection of equipment
  • Testing of alarms
  • Dial-through tests to all stations
  • Test restriction levels, COS
  • Test trunks, T1, tie lines
  • Test call routing & call accounting system
  • Test anti-toll fraud barriers
Slide 16: Postcutover Followup
Slide 16 / 16

Postcutover Followup

  • First few days following cutover are crucial to system
  • Verify all documentation
  • Establish a system for maintaining records
  • Analyze trouble reports