TM Chapter 21 |
|
Jimmy Shaw Jason Martin |
|
Seth Anderson
Kristina Dahl |
|
|
|
|
|
Transition from an old system to a new one |
|
Disrupts organization |
|
Object is to minimize disruption through
planning |
|
New system should make employees more productive
with proper training on new system. |
|
|
|
|
Divide and conquer tasks with teams |
|
Decide whether to re-use some existing
facilities |
|
Train users how to operate new equipment |
|
|
|
|
|
Develop information for programming switch or
network |
|
establish standards |
|
determine storage space |
|
Floor plans should show telecom outlet locations |
|
station types |
|
port assignments |
|
other identifying info |
|
|
|
|
|
System Procurement |
|
Determine system requirements |
|
Develop requests for proposals |
|
Select the system |
|
Negotiate contract |
|
|
|
|
|
Cutover Planning |
|
Determine trunk transition methods &
quantities |
|
Plan station requirements |
|
Develop training plan & cutover schedule |
|
Develop testing methods & security measures |
|
Develop station numbering plan |
|
|
|
|
|
|
|
Station Work |
|
Conduct station reviews |
|
Develop class of service plan |
|
Develop wiring plan |
|
Develop voice mail plans |
|
Assign station numbers |
|
Place station wiring and equipment |
|
Install software |
|
|
|
|
|
Equipment Room |
|
Select Location |
|
Prepare equipment room |
|
Prepare electrical wiring |
|
Prepare HVAC |
|
|
|
|
|
Equipment Installation |
|
Place equipment and trunk orders |
|
Install equipment |
|
Test equipment |
|
Conduct acceptance testing |
|
|
|
|
|
Initialize Software |
|
Prepare station & trunk translations |
|
Program least-cost routing |
|
Prepare toll fraud barriers |
|
Set up voice mail boxes |
|
Initialize call accounting software |
|
|
|
|
|
|
|
Operational Functions |
|
Develop contingency & intercept plans |
|
Reprint telephone directory & stationary |
|
Set up help desk |
|
Develop trouble reporting procedures |
|
Train users |
|
|
|
|
|
|
|
Postcutover Activities |
|
Follow up on training effectiveness |
|
Check on least cost routing |
|
Follow up on trunk quantities |
|
Check billing |
|
Accept system (or reject it!) |
|
|
|
|
|
Most PBXs offer 5 types of terminals: |
|
Single-line analog set |
|
Single-line digital set with feature buttons |
|
Multiple-line set with feature buttons |
|
Multiple-line set with digital display |
|
ISDN set |
|
|
|
|
|
A fall back plan is necessary |
|
What is probability of delay? |
|
What other projects depend on plan completion? |
|
What factors could cause delay? |
|
What alternatives are available to hold the
schedule despite delays? |
|
|
|
|
Physical inspection of equipment |
|
Testing of alarms |
|
Dial-through tests to all stations |
|
Test restriction levels, COS |
|
Test trunks, T1, tie lines |
|
Test call routing & call accounting system |
|
Test anti-toll fraud barriers |
|
|
|
|
First few days following cutover are crucial to
system |
|
Verify all documentation |
|
Establish a system for maintaining records |
|
Analyze trouble reports |
|